Project Description
Scope of work includes:
The installation of the new FWKO is to be completed in three stages. Stage 1 The first stage of the project will be to complete all relevant piping and construction work that can be done without affecting the operation of the existing FWKO vessels V-1-1/102. Stage 2 The second stage of construction involves completing all work necesary to place V-100 in service including the tie-in of a new common inlet line with meter run, road crossing and inlet header. Stage 3 The third stage of the project will include installing separate gas make up and vapor recovery systems on V-101/102 while the vessels are out of service and replacement of the water discharge header from V-101 and 102.
|