Project Description
The work comprised of two concurrent phases. Phase I required repairs to spalling concrete parapet walls, removing and replacing lanai handrail and installation of new sliding glass doors with new interior framing. Phase II is the addition of a pedestrian walkway bridge from the large landi on level 3 into the Outrigger Reef Ocean Tower. Selective demolition of existing guest rooms and construction of a 37' long 6' wide elevated cast in place walkway are underway. Phase III was added via Change Order, adding concrete topping slab waterproofing and framed bollards.
|
Contact
Contact ProjectPhone: (808) 922-2499
Fax: (808) 922-2494
OwnerORF, LLC
DesignerQuad Design Group, Inc.
|
| Site Design and Build by Impello Inc. | Copyright © 2005 PCL Constructors Inc. All rights reserved. |